Double
Eagle
Joint
Board & Renovation Committee Meeting
Telephonic
Committee Meeting
Thursday,
July 12, 2007
MINUTES
FIRST DRAFT
Provided
by Mike Lindseth
Minutes
of the previous meeting
Posted
for review by the Renovation Committee and to inform owners about
the meeting.
Final
approval of these minutes will be made at the next committee meeting.
Return
to What's
New
Participating in the meeting were:
Mike Lindseth, Darnell Boehm, Jerry Niegelsen, Jon Shultz, Brian
Thompson, Fiona Halfon, and Bruce Katz.
The meeting began at 7:00pm CST and ended at 8:00pm CST.
Discussion items:
Painting entrance doors-original bid included one side only-both
sides would be about $400 more in total-Change approved.
Exterior door color recommendation-Fiona recommended "Pella
Brick Red"-Approved
Metal deck railing supports were installed incorrectly in all of the
concrete decks-contractor will need to correct which will probably
result in some of the decks being redone again!
Request by some owners to paint/stain interior lockers-recommendation
to use stain with the polyurethane included in the same coat---Approved
Bill from Pella for Windows came in as quoted, bill for owner option
sliding glass doors came in $3700 higher than quote because Travis
ordered custom size doors-Travis has agreed to credit the project
back $3500 because we could have used trim to avoid the custom
size-Thanks Darnell for working this issue through to a great outcome
with Travis!
Darnell requested approval for reimbursement for the following items:
Use of electric service from Darnell' condo for the project (avoided
paying $1000 for special service brought in)-cost is 3 months of $150/month---Approved
Replace wheelbarrow-Approved
Replace vacuum cleaner-Approve
Status of Project Costs
Cost overruns:
Material for Port Cochere is up $20k because of needing to use
heavier timbers for both support and better appearance
Electric is up $5k to bring power to Port Cochere, hot tub and to
bring stairway lighting back up to code
Costs under:
Gas line moves should be $6k less than budget
Permits are $3k less
Supervisor time is running $10-15k less
Digging trench and painting existing sliding glass doors $5k less
Have 3% contingency as buffer that we will probably not use all of
Overall Darnell feels that the project will be brought in on budget
assuming we don't have any unforeseen issues.
Completed items
Trench(s) under B building
Existing windows and sliding glass doors-3 coats paint
Hot tub decking
2nd and 3rd floor siding on both buildings
Decks, stairways and railings
Chimneys are shortened and squared off
Cable for TV is pulled through the exterior-interior work yet to be done
Exterior doors in except for A-01 which will be installed when
concrete work is done
Window well and deck structure around A-01 is done
In progress items
Rock siding is 80% complete on B building
Gas meters are moved and ready to be reinstalled by Gas Company
Port Cochere is being framed
Will now do landscaping work the 3rd week of August
Sprinkler system will need major overhaul
Trench for hot tub needs to be dug
Inside trim in units
Overall project is progressing on time and on budget-YEAH!!!!!!
Go
to top
of page
Return
to What's
New |